The Challenge
The roof system was compromised and the Tectum decking was completely saturated. This on-going problem caused the growth of mold on the underside of the decking in several areas of the school building including hallways and the school library. The mold had to be removed and the school wanted to eliminate the re-growth of the mold.
The roof system was compromised and the Tectum decking was completely saturated. This on-going problem caused the growth of mold on the underside of the decking in several areas of the school building including hallways and the school library. The mold had to be removed and the school wanted to eliminate the re-growth of the mold.
|
The Solution
The decking was cleaned and a new roof was installed over the Tectum deck. ECI cleaned and disinfected the entire mold infected areas inside the school. We then applied one coat of our FiberTech F-50MR Mold Resistant primer followed by two coats of our FiberTech F-51MR Mold Resistant Sealer Coat. This provided the school with the solution they were looking for.
The decking was cleaned and a new roof was installed over the Tectum deck. ECI cleaned and disinfected the entire mold infected areas inside the school. We then applied one coat of our FiberTech F-50MR Mold Resistant primer followed by two coats of our FiberTech F-51MR Mold Resistant Sealer Coat. This provided the school with the solution they were looking for.